Top

Հայ |  Рус |  Eng

28.11.2012

The ANPP restarted the electricity production

The ANPP restarted the electricity production

On November 27, at 3.20 am, Armenian Nuclear Power Plant restarted working and joined the network of public generate electricity. Note, that the plant's electricity production was suspended on September 15, in order to overhaul, insertion of security arrangements and recharge. The capital repair works must be realized every four years.

The capital repair works and annual planned repair works differ in their duration. The first needs more time, because, in this case the all fuel of the reactor needs to be discharged, in order to accomplish most important works.

During this period, there were carried out plant’s reactor’s corpus inspection, third turbo-generator’s reconstruction works, as well as there were inserted  the whole security arrangements introduced by the program.